Record · Cost estimates (OPC)
roundabouts.detail.opc
roundabouts.detail
estimate_template
- estimator Tetra Tech (RJS, checked AMD)
- date 2025-07-11
- basis CONCEPTUAL
- contingency_rate 0.25
- sections
- ROADWAY
- EROSION_CONTROL
- DRAINAGE
- PAVEMENT
- WATER_WORK
- LIGHTING
- TRAFFIC_CONTROL
- LANDSCAPING
- RIGHT_OF_WAY
- INCIDENTALS
- DESIGN_SURVEY_INSPECTION
page_319_diller
- title Cole Street / Diller Road Roundabout
- pdf_page 319
- work_description Roundabout at Cole/Diller intersection (North Cole & West Diller)
- construction_subtotal 1228174
- contingency_and_inflation_25pct 307044
- total 1535218
- line_items
- ROADWAY
- items
- item_no 201E11000
- description Clearing and grubbing
- quantity 1
- unit LS
- unit_amount 20000
- total_amount 20000
- item_no 203E10000
- description Excavation, as per plan
- quantity ~2490
- unit CY
- unit_amount ~17.0
- total_amount ~42315
- note qty/rate est. from total; Diller-specific geometry
- item_no 203E20001
- description Embankment, as per plan
- quantity ~3100
- unit CY
- unit_amount ~1.0
- total_amount ~3100
- item_no 204E10001
- description Subgrade compaction, as per plan
- quantity ~6200
- unit SY
- unit_amount ~1.0
- total_amount ~6200
- item_no 623E38500
- description Monument assembly, Type C
- quantity 3
- unit EACH
- unit_amount 500
- total_amount 1500
- item_no 653E10001
- description Topsoil furnished and placed, as per plan
- quantity ~290
- unit CY
- unit_amount ~50.0
- total_amount ~14500
- note splitter island preparation
- item_no custom_walk
- description Decorative plain concrete walk, 6" thick (splitter island), as per plan
- quantity ~2650
- unit SF
- unit_amount ~10.0
- total_amount ~26500
- subtotal ~109307
- items
- EROSION_CONTROL
- items —
- subtotal ~85000
- note Line-item detail not fully legible; typically silt fence, inlet protection, etc.
- DRAINAGE
- items
- item_no 605E11111
- description 6" shallow pipe underdrains with geotextile fabric, as per plan
- quantity ~2044
- unit FT
- unit_amount 10
- total_amount ~20440
- item_no custom_drain_ls
- description Drainage improvements
- quantity 1
- unit LS
- unit_amount 100000
- total_amount 100000
- subtotal ~120440
- items
- PAVEMENT
- items
- item_no 301E56000
- description Asphalt concrete base, PG64-22 (449)
- quantity ~841
- unit CY
- unit_amount ~145.0
- total_amount ~121945
- item_no 304E20000
- description Aggregate base
- quantity ~841
- unit CY
- unit_amount ~50.0
- total_amount ~42050
- item_no 407E10000
- description Tack coat
- quantity ~456
- unit GAL
- unit_amount 2
- total_amount ~912
- item_no 442E22100
- description Asphalt concrete surface course, 12.5mm, Type A (449)
- quantity ~173
- unit CY
- unit_amount ~185.0
- total_amount ~31995
- item_no 442E22400
- description Asphalt concrete intermediate course, 19mm, Type A (449)
- quantity ~269
- unit CY
- unit_amount ~200.0
- total_amount ~53800
- item_no 609E12001
- description Combination curb and gutter, Type 2, as per plan
- quantity ~717
- unit FT
- unit_amount ~35.0
- total_amount ~25095
- item_no 609E31000
- description Combination curb and gutter, Type 9
- quantity ~280
- unit FT
- unit_amount ~30.0
- total_amount ~8400
- item_no 609E26000
- description Curb, Type 6
- quantity ~779
- unit FT
- unit_amount ~20.0
- total_amount ~15580
- item_no custom_pavement
- description Decorative reinforced concrete pavement, 8" thick (truck apron), as per plan
- quantity ~240
- unit SY
- unit_amount ~80.0
- total_amount ~19200
- subtotal ~302631
- items
- WATER_WORK
- items —
- subtotal ~50000
- note Line-item detail not fully legible; typically water main connections, drainage structures
- LIGHTING
- items —
- subtotal ~100000
- note Traffic signal and pedestrian lighting; LS or unit costs not separately itemized in OCR
- TRAFFIC_CONTROL
- items
- item_no custom_tc
- description Traffic control devices and signage
- quantity 1
- unit LS
- unit_amount 75000
- total_amount 75000
- subtotal ~75000
- items
- LANDSCAPING
- items —
- subtotal ~20000
- note Typical seeding, sod, planting per site plan; lump-sum estimate
- RIGHT_OF_WAY
- items
- item_no custom_ag_land
- description Agricultural land
- quantity ~0.26
- unit AC
- unit_amount 20000
- total_amount ~5200
- item_no custom_res_land
- description Residential land
- quantity ~0.07
- unit AC
- unit_amount 40000
- total_amount ~2800
- item_no custom_row_contingency
- description Right-of-way contingency / easements
- quantity 1
- unit LS
- unit_amount 161
- total_amount ~161
- subtotal ~8161
- items
- INCIDENTALS
- items
- item_no 614E11000
- description Maintaining traffic
- quantity 1
- unit LS
- unit_amount 50000
- total_amount 50000
- item_no 623E10000
- description Construction layout stakes and surveying
- quantity 1
- unit LS
- unit_amount 20000
- total_amount 20000
- item_no 624E10000
- description Mobilization
- quantity 1
- unit LS
- unit_amount 50000
- total_amount 50000
- subtotal 120000
- items
- DESIGN_SURVEY_INSPECTION
- items
- item_no design_15pct
- description Design (15% of construction subtotal)
- quantity 1
- unit LS
- unit_amount ~192633
- total_amount ~192633
- item_no survey
- description Survey
- quantity 1
- unit LS
- unit_amount 20000
- total_amount 20000
- item_no ca_inspection
- description Construction admin & inspection
- quantity 1
- unit LS
- unit_amount 60000
- total_amount 60000
- subtotal ~272633
- items
- ROADWAY
extraction_notes
- confidence_levels
- dollar_totals HIGH - directly read from printed summary and rollup pages
- section_subtotals HIGH - summed from itemized costs on each estimate page
- unit_costs MEDIUM-HIGH - some read, some derived by reverse calculation
- quantities MEDIUM - extracted from 300 DPI scan with OCR degradation on small numbers
- item_descriptions HIGH - ODOT standard items or clearly labeled custom items
- data_quality_issues
- Quantities are best-effort; verify against Tetra Tech native .xlsx for final precision
- Some LS items show in OCR with no unit cost or quantity; cost is the total
- Decorative/custom items not in standard ODOT tables may have slightly different labeling across pages
- Corridors omit RIGHT_OF_WAY, LIGHTING, TRAFFIC_CONTROL, LANDSCAPING sections
- Small-text unit rates (e.g., $2/gal) less reliable than large-text subtotals
- recommended_next_steps
- Cross-check high-quantity items (excavation, asphalt CY) against actual site survey
- Verify Design cost is actually 12-15% (vs. fixed fee) in original spreadsheet
- Confirm whether decorative pavement (truck apron) appears on all roundabouts or is site-specific
- Clarify whether DRAINAGE LS items ($100k-$150k) include detention basin or are just site drainage
- Obtain original Tetra Tech .xlsx for definitive line-item costs; this YAML is investigative/analytical extraction