Watermark.
Lima BOSC
Switch site 38 sites · 11 basins 8 open

Each site is one Watermark investigation. The page color says what opens; the campus line is the build on the ground — two different clocks.

MAU Maumee Basin 9 sites
2MI The Two Miamis 9 sites
SE Southeastern Basins 12 sites
NE Northeast Basins 8 sites
The page — what opens on Watermark Open · Draftfull record Queued · Watchingpreview page Restrictedrequest access
The campus — the build on the ground Investigating Confirmed Under construction Operational
All 38 sites — the network index →
Building
The record
Record · Permits

American II Wastewater Treatment Plant

oepa-2PH00006-american-ii-permit
[verified]
Fields
facility_name
American II Wastewater Treatment Plant
permit_no
2PH00006*LD
permit_action
renewal
applicant
Allen County Board of Commissioners
application_no
OH0037338
public_notice_no
public_notice_date
comment_period_end
facility_address
4140 Diller Road, Lima, Ohio, Allen County
discharge_address
receiving_water
Dug Run at River Mile 3.1
stream_network
note
Action date June 17, 2025; permit effective August 1, 2025; expires July 31, 2030. Two discharge periods: Initial (first 36 months) and Final (month 37 through expiration), with toxicity limits added in Final period. Design flow 1.2 MGD.
outfalls
  • 2PH00006001
⚠ Gaps in the record
  • No public notice number, public notice date, or comment period end date found in the document — it carries no public notice block at all. public_notice_date previously held 2025-06-17, which is the ACTION date printed on the permit (now retained in note); the extractor recorded it knowing it was "not necessarily a formal public notice date", so it is corrected to null (#1405 review).
  • No downstream stream network chain stated beyond Dug Run
Where it connects
oepa/oepa-2PH00006-american-ii-permit.npdes.yaml · p.1 · oepa