Watermark.
Lima BOSC
Switch site 38 sites · 11 basins 8 open

Each site is one Watermark investigation. The page color says what opens; the campus line is the build on the ground — two different clocks.

MAU Maumee Basin 9 sites
2MI The Two Miamis 9 sites
SE Southeastern Basins 12 sites
NE Northeast Basins 8 sites
The page — what opens on Watermark Open · Draftfull record Queued · Watchingpreview page Restrictedrequest access
The campus — the build on the ground Investigating Confirmed Under construction Operational
All 38 sites — the network index →
Building
The record
Record · Enforcement

extension letter

edoc-3170400
[verified]
Fields
agency
Ohio EPA (OEPA-Northwest District)
instrument
extension letter
case_no
respondent
City of Lima, Ohio
facility
City of Lima Lift Stations (all 30 lift stations, including Cable Road and Hickory Knoll)
permit_no
2PE00000*MD
issued_date
2014-12-08
effective_date
supersedes
NPDES Permit 2PE00000*MD, Part I, C.b compliance schedule (original January 1, 2015 deadline for Cable Road and Hickory Knoll lift stations)
penalty_usd
stipulated_penalties
status
active
summary
The City of Lima's Environmental Compliance Manager, David L. Schnipke, writes to OEPA-Northwest District requesting a time extension under NPDES Permit 2PE00000*MD, Part I, C.b for two lift stations (Cable Road and Hickory Knoll) that cannot meet the original January 1, 2015 completion deadline due to construction difficulties and an easement acquisition issue. The letter requests a new completion deadline of April 1, 2015 for those two stations, noting that 11 of 30 total lift stations are already complete and all are expected to be finished by April 14, 2015.
note
Bears URS Project No. 14578549 (the consulting engineer's own file number) and cites permit 2PE00000*MD.
obligations
    • requirement Complete improvements to Cable Road lift station
    • deadline 2015-04-01
    • status extended (original deadline 2015-01-01)
    • requirement Complete improvements to Hickory Knoll lift station
    • deadline 2015-04-01
    • status extended (original deadline 2015-01-01)
    • requirement Complete improvements to all 30 lift stations (overall program)
    • deadline 2015-04-14
    • status in progress (11 of 30 completed as of letter date)
    • requirement Complete improvements to Allentown Road, Lost Creek, Gloria Road, and Sugar Street lift stations (NPDES Part I, C.b listed stations)
    • deadline
    • status completed
⚠ Gaps in the record
  • case_no NULLED — it held 'URS Project No. 14578549', the CONSULTANT'S internal project number. It is printed on the letter and is real, but it is not a case or docket number and putting it in a join key would group this letter with nothing. Kept in the note instead.
  • Permit number reads '2PE00000*MD' — the asterisk may represent additional digits not fully legible; verified against image and OCR appears consistent.
  • OCR renders 'complete' as 'complet' in one instance — confirmed as OCR artifact only.
  • Overall program completion date given as 'April 14, 2015' in the first paragraph, while the specific extension request deadline is 'April 1, 2015' — both dates captured as stated.