Each site is one Watermark investigation. The page color says what opens; the campus line is the build on the ground — two different clocks.

MAU Maumee Basin 9 sites
2MI The Two Miamis 9 sites
SE Southeastern Basins 12 sites
NE Northeast Basins 8 sites
The page — what opens on Watermark Open · Draftfull record Queued · Watchingpreview page Restrictedrequest access
The campus — the build on the ground Investigating Confirmed Under construction Operational
All 38 sites — the network index →
Building

← The record · Legal history

County governance

Allen County Commissioners — the legislative record

The Board of County Commissioners’ own meeting record (2023–2026), mined from the minutes corpus (933 raw PDFs + the OCR’d parquet index) into the legislative spine of Project BOSC, its closed-deliberation mechanics, and the wastewater economics the County deferred on in the public-records production.

Artifacts

FileWhat
bosc-resolution-ledger.yamlThe project’s legislative spine, keyed by resolution # → date → verbatim title → mover: NDA #417-25, CRA #548-25, RDA #588-25, the Sanitary Sewer Developer Agreement #575-25 (amended #975-25), pump-station/forcemain engineering #469-25 → #713-25 → CMAR #137-26/#138-26, the BOSC Fund #612-25 — plus the codename-phase narrative and the wastewater-works resolutions.
closed-deliberation-and-corridor.yamlThe executive-session (closed-deliberation) census, by ORC 121.22(G)(n) exemption. The economic-development (G)(8) sessions first appear 2025-05-27 (the BOSC CRA, expressly citing the NDA) and never before in the covered record. Plus the land/right-of-way corridor (Hamlet of Hume sewer, ODOT roundabout ROW, force-main easements).
sanitary-economics.yamlThe wastewater thread in dollars and flow: the BOSC sanitary load (0.13 MGD @ 83 °F interim), the ~$32M developer pump station + ~$3.125M capital permit fee, and the Cridersville/Shawnee Oaks revenue-capture reroute ($1M 0% loan; ends a $102k/yr outflow).
bosc-water-balance.analysis.mdThe Tier-0 water-balance run + 7Q10 assimilative screen with those sanitary figures folded in — all three receiving streams already fail the low-flow dilution screen before any BOSC load.
bosc-2023-backfill.yamlThe pre-BOSC baseline year: the 2023 record is silent on the data center; what’s present is the precursor machinery (Shawnee II Phase 2, the annual AEDG EZ/CRA contract, routine abatements, EMH&T, the Hamlet of Hume sewer origin).
minutes/The underlying minutes/agenda corpus + the OCR parquet index bundle.

Provenance

Resolution numbers, titles, dates, and movers are high-confidence (verbatim from the formal resolution lists); discussion-item figures are OCR-approximate — verify against the source PDF before quoting. Coverage is 2024–2026 in the committed parquet; 2023 was mined via ad-hoc OCR (see the backfill). These artifacts carry kinds the corpus loader does not recognize, so they are read directly by the timeline assembler.