MWCD board award votes + Norfolk Southern bid opening fall on 2026-07-14 — capture the outcomes
The two cornerstone flood contracts bid 2026-06-30 with apparent low bidders only — Miller Brothers Construction at $32,075,000 for the Eagle Creek Dry Storage Basin (est. $42,376,000) and Helms & Sons at $3,699,040 for the Phase 2 downtown benching / Additional Hydraulic Improvements (est. $6,170,000). The Maumee Watershed Conservancy District Board of Directors was to consider award recommendations at its 9:00 a.m. 2026-07-14 meeting in Defiance; the Norfolk Southern bridge bid opening was extended to 2026-07-14 at NS headquarters in Atlanta. As of ingest neither outcome was published. OPEN — do not upgrade "apparent low" to "awarded" without the board minutes; pull the 07-14 results and the NS bid tabulation and add award rows.